Two meters can start running when your container reaches Israel, and most people learn their names from an invoice. Learn them here instead. They are the most avoidable serious cost in international moving. Figures differ by port, carrier and year, so rely on the schedule in your own quote.
Meter one: port storage
The port charges for the ground your shipment occupies. A container of your own gets only a short free period, counted in days, and after that a daily rate that escalates over time. Shared (LCL) shipments generally get a much longer free window, which is why we point families who are still apartment-hunting toward a shared container. One trap inside the trap: a container that reaches Israel indirectly, transshipped through another port, can get an even shorter free period.
Meter two: demurrage
Separate from the port, the shipping line charges rent on its container itself, typically starting soon after arrival and escalating in bands the longer the box sits. Different carriers have different schedules but the same principle: the container is their asset, and they price your delay. Demurrage follows the carrier’s tariff, and no shipper can waive it. The honest ones just show you the schedule up front.
How delays actually happen (it’s rarely laziness)
- Something owed hasn’t been paid, so delivery can’t be scheduled.
- The apartment isn’t ready, or the lift or crane slot isn’t booked.
- Customs selects the container for inspection.
- Paperwork arrives late (a missing signed form can cost a week).
- The customer is abroad and unreachable while clearance is under way.
Notice the pattern: most of these can be scheduled in advance. That is the entire defense.
The defense, as a checklist
- Settle what you owe promptly. Under our contract, you pay the quoted price when you sign, so by arrival the only things outstanding are usually extras. Delivery is scheduled once everything due before delivery is paid.
- Do documents at signing, not at arrival. We collect the customs paperwork early, and your customs broker may ask you directly for more. Answer promptly.
- Plan delivery logistics ahead. Check access, book any crane or lift, and have someone with keys on call.
- Know the ETA. You can’t prepare for a date you don’t know. That is half the point of our updates at least every 7 days.
- If a wait is unavoidable (the apartment closes next month), decide in advance between port charges and moving the goods to a storage facility. A calm comparison beats a panicked one on day six.
Who pays?
Under our contract, port storage, terminal storage and demurrage are pass-through charges where they arise from a delay caused by you, by an official authority or by an inspection. We bill them at documented cost, with a copy of the supplier’s invoice. If a delay is our or our subcontractors’ fault, you don’t pay it.
What to demand from any quote
The storage and demurrage schedules in writing, before you sign: the free days, the daily bands, and the handling fees around them. A company that attaches these unprompted is telling you how it will behave in week nine.